A producer of high quality deli meats, cheeses and condiments needed to expand and renovate a 500,000-square-feet, existing food production facility in Jarratt, VA and save energy in the process. All this would need to be accomplished while remaining fully operational.

The designers, engineers and construction experts at A M King had their work cut out for them.

Because the facility could not shut down while we worked, we developed a logistics plan that included 24/7 supervision and mission critical food barrier practices to allow construction to take place. We then installed specialty floor slabs, dropped ceilings from 20 feet to 15 feet to save energy in the food storage area and organized a state-of-the-art ammonia refrigeration system. The new drive-through dock operations allowed for greater thermal control in the new dock facility as well.

The benefits to the customer were numerous. First and foremost was the 30 percent increase of meat product production and the ability to turn out multiple proteins concurrently. The company also increased its refrigeration capacity by 100 percent, doubled its shipping and receiving capabilities and expanded product storage by 25 percent. They also enjoyed a surge in overall efficiency, improved product flow and greater incoming electrical service.

A M King’s turnkey design, engineering and construction was a recipe for success.


A M King Staff
A M King Staff
Related Blogs
Read Andre Harris' blog to learn about A M King's Design-Build Solutions for Manufacturers.
READ MORE
Apr 7, 2025 • CORPORATE
Design-Build for Manufacturers: Collaboration is King

People that I’m meeting for the first time often ask me how A M King brings value to…

In his latest blog, A M King President Dan Crist shares the key to better integrated design and construction.
READ MORE
Mar 10, 2025 • CORPORATE
The Key to Better Integrated Design and Construction

Construction personnel and design personnel think differently, are wired differently and are definitely different types of people. But…

READ MORE
Dec 9, 2024 • CORPORATE
ASC Design-Build Competition Benefits AEC Students

Last month we provided the project for our fifth Associated Schools of Construction event — the ASC Design-Build…

A M King Senior Designer Chad Elly, AIA, writes about Resilient Design in this month's blog.
READ MORE
Nov 5, 2024 • CORPORATE
The Power of Resilient Design

There is a concept in architecture that continually speaks to me. I’ve seen its absence create constraints, added…

Controlled-temperature facilities
READ MORE
Sep 12, 2024 • CORPORATE
A Very Cool Conversation about Controlled-Temperature Facilities

If you’re a cold foods manufacturer, what is your No. 1 challenge? Is it food safety, facility efficiency,…

READ MORE
May 7, 2024 • CORPORATE
Preparation is Key for Successful Manufacturing Equipment Installation

Several years ago, GE Gas Turbine (now GE Vernova) embarked on a mission to bring four custom-built, 10-ton…

Subscribe To Our Blog

SUBSCRIBE TO OUR BLOG

This field is for validation purposes and should be left unchanged.